This title is printed to order. This book may have been self-published. If so, we cannot guarantee the quality of the content. In the main most books will have gone through the editing process however some may not. We therefore suggest that you be aware of this before ordering this book. If in doubt check either the author or publisher’s details as we are unable to accept any returns unless they are faulty. Please contact us if you have any questions.
On January 15, 2018 at 11:49, the west pylon of the cable-stayed Chirajara Bridge collapsed during construction of the bridge girder. The collapse led to the total destruction of the pylon, together with the erected span of the bridge girder. Authorities reported nine fatalities resulting from the collapse.
In this case study, the findings of the detailed investigation into the failure mechanism of the bridge are reported. In addition, selected drawings used for construction, geotechnical aspects, and deficiencies in the bridge design are presented, together with observations made during site visits and interviews with relevant parties.
$9.00 standard shipping within Australia
FREE standard shipping within Australia for orders over $100.00
Express & International shipping calculated at checkout
This title is printed to order. This book may have been self-published. If so, we cannot guarantee the quality of the content. In the main most books will have gone through the editing process however some may not. We therefore suggest that you be aware of this before ordering this book. If in doubt check either the author or publisher’s details as we are unable to accept any returns unless they are faulty. Please contact us if you have any questions.
On January 15, 2018 at 11:49, the west pylon of the cable-stayed Chirajara Bridge collapsed during construction of the bridge girder. The collapse led to the total destruction of the pylon, together with the erected span of the bridge girder. Authorities reported nine fatalities resulting from the collapse.
In this case study, the findings of the detailed investigation into the failure mechanism of the bridge are reported. In addition, selected drawings used for construction, geotechnical aspects, and deficiencies in the bridge design are presented, together with observations made during site visits and interviews with relevant parties.